This is the process of obtaining the positions of the structural parts of a building in the geometrical construction. The positions of the structural parts of a building can be obtained by detailed structural drawings. These data has to be transferred to the field to start the geometrical construction with sufficient accuracy; enabling independent checks for readily detecting of any errors.
The first step
in building setting out is to identify a base line according to the site layout
plan. We can establish the base line considering the permanent structures and
the relevant distances to structural parts from them as given in the drawings.
Setting out is done based on
the principle of “Whole to part”. According to this principle the largest
possible rectangle of the building is found and set up first. Then it is
further divided into small parts completing the major setting out for the
building.
It is very important that
setting out process is done in a horizontal plane. When the ground profile is
not horizontal proper care must be paid to establish the setting out profiles
in a one level. For simple applications a tube filled with water can be used to
obtain the levels.
Main instruments involved in
this process are Theodolite, Steel and Linen Tapes, Arrows, Wooden pegs, Wire
nails and Nylon threads.
After establishing the base
line, the main rectangle is set up using the pegs and theodolite. Arrows are
used as temporary pegs and wooden pegs are driven for permanent pegs .90° angle
is taken by the theodolite and Pythagoras rule is
also commonly used for the
process. When using the Pythagorasrule
proper care must be paid to obtain the largest possible combination of triangles
for higher accuracy. Steel tape must be used to measure long distances and it
must be tightly stretched when taking the readings.
Wooden pegs atop by a wire nail
are driven to establish the grid lines of the building. These pegs are driven
at places such that they won’t be disturbed by field work etc. Usually they are
driven with a distance of 1.5 meter from the grid line.
The diagonals of the main
rectangle are checked to determine its accuracy. Accurately set up main
rectangle is then subdivided to obtain the consisting gridlines. These are
obtained by the using structural drawings, Theodolite and steel tape. Nylon
threads are stretched between the pegs to obtain the gridlines when necessary.
Usually apart from the pegs
depicting the main grid lines, pegs which show the 500mm off sets are also
established during the setting out process to facilitate the construction that
follows.